Industrial

In addition to supporting the delivery of energy audits at a variety of industrial sites including plastics injection molding, contract food manufacturing, and electronic equipment assembly, AIMS has addressed reporting of site wide and unit operation Key Performance Indicators  and project prisonization.

Water Pumping System ESPC Development

A level 1 assessment to ISO 50002:2014 and ISO/ASME 14414:2019 was conducted at 20  representative pumping stations in the low voltage network of the national water utility of El Salvador (ANDA). The results werethe extrapolated across ANDA's national network of 418 pumping stations.

Electricity consumption data for the 418 sites along with existing asset data was entered into AIMS. The 20 site assessments and their associated site reports were conducted in AIMS. The platform allows any prospective ESPC bidder to rewadily access the assessment and network data.

Internal carbon pricing

Energy audits to ISO 50002:2014  were conducted at two manufacturing sites of a New York stock exchange quoted furniture manufacturer. In addition to identifying over 1/4 million dollars of cost effective savings, over 60 decarbonization projects were quantified and prioritized using AIMS carbon pricing module.